Timeline of Key Events

Refurbishment and Testing of Units, Inverter Assembly: January 15 - April 15
Deadline for RFP submissions: April 15
Select winners of RFP process: May 1 - May 15
Site Evaluations: April 15 - May 15
Site Applications Engineering: May 1 - May 15
Fuel Cell Installations: May 15 - July 15
Wrap Up and Unveiling of 1 Installed Unit: July 15 - July 30